The land-for-flat construction agreement is one of the types of contract that most often gives rise to disputes in practice. The landowner's basic expectation is that the independent units agreed in the contract in return for the land will be completed and handed over in full, free of defects and on time. However, where the contractor never starts construction, leaves it unfinished, misses the delivery date or fails to complete the building in accordance with the contract, the question of what rights the landowner has becomes important.
In this situation the landowner does not have only one option. Depending on the circumstances of the case and the content of the contract, different legal routes may be available, such as requiring completion of the construction, claiming damages for delay, having the construction completed at the contractor's expense, withdrawing from the contract or seeking its termination.
1. The Land-for-Flat Construction Agreement
In terms of its legal nature, the land-for-flat construction agreement is a mixed contract that has the features of both a contract for work and a promise to sell real property.
On one side of the contract, the landowner undertakes to transfer the land or certain land shares to the contractor; on the other, the contractor undertakes to construct and hand over a building on the land in accordance with the contract, the project, zoning legislation and the rules of science and art.
The contractor's obligation is therefore not merely to "physically build the building". The building agreed in the contract must be completed in accordance with the contract and its annexes, the approved project, the building permit, zoning legislation and the rules of science and art, and must be made ready for handover to the landowner.
2. The Landowner's Rights When the Contractor Fails to Complete the Construction
Which right the landowner will exercise if the contractor fails to complete the construction must be determined primarily according to the stage the construction has reached, whether the delivery date has arrived, the contractor's fault and the special provisions of the contract.
The main options are:
- requiring completion of the construction,
- claiming compensation or loss of rent due to the delay,
- claiming a contractual penalty, if one is provided for in the contract,
- having the construction completed by a third party in the name and at the expense of the contractor,
- withdrawing from the contract because the contractor has failed to perform,
- bringing an action for termination of the contract where the circumstances of the case so require,
seeking cancellation of the title registrations of land shares or independent units previously transferred to the contractor and their registration in the landowner's name.
However, these rights cannot all be exercised at the same time or in a contradictory manner. In particular, there are important differences in legal consequences between requiring completion of the construction and withdrawing from or terminating the contract.
3. When It Becomes Clear Before the Delivery Date That the Construction Will Not Be Completed
The landowner does not always have to wait for the delivery date for their rights to arise. Article 473 of the Turkish Code of Obligations allows the employer to act without waiting for the delivery date where it becomes clear that the construction cannot be completed on time because the contractor has not started the work on time or has delayed it in breach of the contract.
In other words, if, for example, the contract provides that the construction will be completed within 24 months but the contractor has not started construction although considerable time has passed, or if it is clearly apparent that the construction cannot be completed on time at its current pace, the landowner may not need to wait for the delivery date.
In addition, if it is clearly apparent while construction is ongoing that the building will be defective or non-compliant with the contract due to the contractor's fault, the landowner may give the contractor a reasonable deadline to remedy the defect or non-compliance and notify them that, failing this, the repair or continuation of the work will be entrusted to a third party.
4. The Contractor's Default When the Delivery Date Passes
If the construction is not completed by the delivery date set in the contract, the contractor's default arises depending on the contract and the circumstances. In bilateral contracts, under Article 123 of the Turkish Code of Obligations (TCO), the defaulting party is as a rule given a reasonable period to perform.
However, granting an additional period is not mandatory in every case. For example,
- where the contractor's conduct shows that granting an additional period would be futile,
- where performance has become useless to the landowner due to the delay,
- where the contract provides that performance will no longer be accepted once the agreed time has passed,
an additional period may not be required under Article 124 TCO. Before resorting directly to termination or withdrawal, the landowner should therefore carefully examine the delivery and default provisions of the contract.
5. The Landowner's Optional Rights When the Contractor Is in Default
In land-for-flat construction agreements, if the contractor does not complete the construction and hand it over to the landowner within the period agreed in the contract, the debtor's default arises.
Once the contractor is in default, the landowner is not obliged to wait for the contractor to perform, that is, to complete the construction.
Article 125 of the Turkish Code of Obligations grants the creditor certain optional rights in bilateral contracts. Accordingly, the creditor may require the defaulting debtor to perform and to compensate the damage caused by the delay, or, if certain conditions are met, may waive performance and claim compensation for the damage arising from non-performance, or withdraw from the contract.
These optional rights are even more important in land-for-flat construction agreements. This is because the landowner's main obligation under such a contract is to transfer certain land shares to the contractor, while the contractor's main obligation is to construct the building agreed in the contract in return for those shares and to hand over the independent units belonging to the landowner.
The contractor's default may therefore not be a simple delay consisting only of the construction not being completed by a certain date. The length of the delay, the current level of construction, the seriousness of the contractor's breach and the extent to which the landowner's expected benefit from the contract has been achieved are all important in determining which optional right the landowner can exercise.
5.1. Requiring Completion of the Construction
The landowner's first option is to require the contractor to perform its construction obligation without ending the contract. In this case, despite the contractor's default, the landowner chooses to keep the contract in force and to have the contractor complete the construction and hand over the independent units due to them.
Where this optional right is exercised, the contractor's obligation is not limited to completing the construction. The contractor is also liable for the consequences of the delay during the period of default. In other words, requiring specific performance does not, as a rule, prevent the landowner from claiming the damage suffered due to the delay. The landowner may therefore, on the one hand, require completion of the construction and handover of their independent units and, on the other, claim compensation for the legally recoverable damage suffered as a result of the default.
For example, if the landowner was unable to use an independent unit or let it to third parties because it was not handed over on the date required by the contract, it may be possible, depending on the circumstances, to claim the resulting loss of rent. Here, the loss of rent must actually have occurred, there must be an adequate causal link between the contractor's delay and the damage, and the amount of the damage must be demonstrable. Likewise, reasonable and direct expenses, such as the landowner having to rent another home or workplace because of the delay, may be considered within the scope of compensation depending on the circumstances.
However, requiring completion of the construction does not mean that the contractor is given unlimited time. If the contractor's default continues and confidence that the contract will be properly performed is lost, the landowner may turn to the other optional rights. The nature and length of the delay and whether the landowner's expected benefit from the contract can still be achieved are therefore important in each case.
5.2. Waiving Performance and Claiming Compensation
The landowner's second option is to stop requiring the contractor to complete the construction and instead claim compensation for the damage arising from non-performance. With this optional right, rather than waiting for the contract to be performed, the landowner chooses to have the economic consequences of the contractor's failure to perform remedied.
There is a difference here between "waiving performance" and merely not wishing to wait any longer for the contractor. By exercising a legally recognised optional right, the landowner makes clear that they will no longer require the contractor's main performance and instead claims compensation for the damage arising from non-performance (the failure to complete the construction on time). It is therefore important to state clearly and unambiguously which optional right is being exercised.
In this case, the extent of the damage to be compensated is determined by taking into account the actual loss suffered by the landowner and the economic benefits lost because the contract was not properly performed.
Nevertheless, it cannot be said that every economic loss will be compensated directly. The existence and amount of the damage, the adequate causal link between the contractor's default and the damage, and whether the compensation is legally claimable must be assessed separately.
In land-for-flat construction agreements, waiving performance may become important particularly where completion of the construction by the contractor is no longer meaningful or possible for the landowner. For example, where the construction has not progressed at all for a long time, the contractor has become financially or practically unable to perform, or the delay has defeated the economic purpose the landowner expected from the contract, the landowner may seek compensation rather than waiting for completion.
However, the right to waive performance and claim compensation must be distinguished from the right to withdraw from the contract. When waiving performance, the landowner essentially gives up the claim for performance and seeks compensation for the damage arising from non-performance. When withdrawing from the contract, the contractual relationship is ended, and liquidation consequences arise, such as the return of what the parties have already performed. Correctly identifying the legal nature of the landowner's claim is therefore of great importance, particularly as regards the fate of land shares already transferred to the contractor.
In addition, when the landowner exercises the right to withdraw from the contract, if the contractor cannot prove that it was not at fault for failing to complete the construction on time, the landowner may, alongside withdrawal, also claim compensation for the damage suffered because the contract became void.
5.3. Withdrawing from the Contract or Seeking Termination
The landowner's third option is to end the contractual relationship if the conditions are met. The right to withdraw becomes important where the contractor's default continues and the landowner can no longer reasonably be expected to wait for performance. However, in land-for-flat construction agreements, ending the contract may have more complex consequences than in other types of contract. The main reason is the reciprocal and unique structure of the contract, which involves both the transfer of land shares and an obligation to build and hand over a building.
At this point, the concepts of withdrawal and termination must first be distinguished. Withdrawal is, as a rule, a legal institution that ends the contract retroactively and allows the parties to reclaim what they have given. Termination, by contrast, ends the contract with effect for the future, particularly in continuing obligations.
In land-for-flat construction agreements, which institution applies must be determined according to the nature of the contract, the extent to which the parties have performed their obligations and the level the construction has reached.
In particular, where the construction is still at or near the initial stage, the contractor has not performed a significant part of its obligation and the purpose expected from the contract has not yet been achieved, ending the contract retroactively (withdrawal) comes into play. In this case, the performances the parties have given each other under the contract are returned. For the landowner, the most important consequence is the ability to claim the re-transfer of the land shares previously transferred to the contractor.
By contrast, where the construction is largely complete, the contractor has performed a significant part of its contractual obligation and the independent units have come into existence economically and physically, ending the contract with effect for the future (termination) comes into play.
The mere fact that the contractor is in default does not therefore mean that the same legal consequence will follow in every case. The court must assess together the completion rate of the construction, the nature and economic value of the work carried out, the seriousness of the contractor's breach, the benefit the landowner expected from the contract and the extent of the performances the parties have given so far.
6. Completion of the Construction by the Landowner or Another Contractor
Under Article 113 TCO, where the debtor fails to perform an obligation to do something, the creditor may ask the court for permission to have the performance carried out by themselves or by a third party at the debtor's expense. In practice, this is referred to as "performance in the debtor's name".
For example, the contractor may have left the building at 80% completion, but the landowner may prefer to have the building completed rather than end the contract. In such a case, the court may be asked to determine the incomplete work and, where the necessary conditions are met, to rule that it be completed by the landowner or by another contractor.
What matters here is that the landowner can correctly establish which works are incomplete and how much it will cost to complete them. Expert examination is therefore important, particularly on technical matters.
7. Can the Contractor Claim Transfer of Title Before Completing the Construction?
Under the principle of simultaneous performance (the defence of non-performance) set out in Article 97 TCO, in bilateral contracts one party cannot require the other party's performance without performing its own obligation, unless the nature of the contract requires otherwise.
This principle has an important consequence in land-for-flat construction agreements. As a rule, the contractor cannot claim the transfer of the independent units or land shares agreed to be left to it without first performing its obligation to construct and hand over the building in accordance with the contract.
The Assembly of Civil Chambers of the Court of Cassation also states that the contractor's performance of its own obligation in accordance with the contract, the project, the permit, zoning legislation and the rules of science and art is important for a claim for registration (Court of Cassation, Assembly of Civil Chambers, E. 2023/293, K. 2024/107, 14.02.2024).
Therefore, if the contractor leaves the construction incomplete, the landowner may refrain from transferring title shares that it is not yet obliged to transfer under the contract.
8. Transfer of the Contractor's Rights to a Third Party
In land-for-flat construction agreements, the contractor's transfer to third parties of the land shares or independent units left to it causes significant legal problems in practice. In particular, it was debated for many years whether the acquisitions of third parties who bought land shares or independent units from the contractor would be protected where the contractor fails to complete the construction, the contract is invalid or the landowner ends the contract retroactively.
The Court of Cassation's practice on this issue was significantly changed by the decision of the Grand General Assembly on the Unification of Case Law dated 16.05.2025, E. 2024/1, K. 2025/2.
Under the previous settled practice of the Court of Cassation, transfers of land shares by the landowner to the contractor under a land-for-flat construction agreement were mostly treated as "advances". Accordingly, if the contractor did not properly perform its construction obligation and the contract ended retroactively, the legal basis for the transfer of land shares to the contractor was considered to have ceased to exist.
The fact that the contractor had transferred these shares to third parties did not change the result. Under the old practice, third parties' arguments that they had acquired rights in good faith in reliance on the land registry were in most cases not accepted, and the landowner could seek cancellation of the shares transferred to third parties and their registration in its own name.
The Grand General Assembly on the Unification of Case Law departed from the previous practice and ruled that the legal position of third parties must be assessed according to the circumstances of each case.
The key consequence of the decision is as follows: after the property subject to the land-for-flat construction agreement has been transferred to the contractor in the land registry, if the contractor sells those land shares or independent units to third parties or establishes a mortgage in favour of a third party, a finding that the contract between the landowner and the contractor is invalid, or the retroactive ending of the contract, does not automatically extinguish the third party's right in rem.
The third party may argue that it acquired the right in rem in good faith in reliance on the land registry, and the court will investigate this argument. If it cannot be proven that the third party acted in bad faith at the time of acquisition, its ownership or mortgage right will have to be protected under Article 1023 of the Turkish Civil Code (TCC).
An important legal distinction must also be made here. The contractor's transaction with a third party may not always take the form of a direct transfer of title. The contractor may also transfer its right to an independent unit arising from the land-for-flat construction agreement to a third party by way of assignment of receivables.
Under Articles 183 et seq. of the Turkish Code of Obligations, the assignment of a receivable does not, as a rule, require the consent of the debtor, that is, the landowner. Under Article 184 TCO, an assignment must be made in writing to be valid. However, the right held by the third party here is not the same as a right in rem acquired directly in reliance on the land registry.
As a rule, the assignee succeeds to the right held by the contractor. Consequently, for the contractor to acquire rights from the landowner, it must have performed its obligations under the contract.
Indeed, Court of Cassation practice accepts that, for a person who has taken an assignment of an independent-unit claim from the contractor to require that the unit earned by the contractor be given to them, the state of performance of the contract must be examined separately.
9. Contractual Penalty Provisions
If the contract provides for a contractual penalty for the contractor's delay or failure to perform properly, the landowner may claim this amount once the conditions are met.
In particular, provisions such as
- a delay penalty set for each month,
- a penalty set per independent unit,
- a penalty for non-performance or improper performance of the contract
are important in practice.
Under Article 179 TCO, whether a contractual penalty can be claimed depends on which breach the penalty is linked to and on the nature of the contractual provision.
For example, if a delay penalty has been agreed, whether the landowner waived its rights when accepting the delay may become important. Correspondence, formal notices, handover records and other documents produced during the delay are therefore important.
10. Termination of the Contract
In land-for-flat construction agreements, termination must be handled more carefully than termination of an ordinary contract for work. Because the contract also contains provisions on the transfer of real property, ending it may affect the land registry records, particularly where shares or independent units have already been transferred to the contractor.
Termination of the contract does not have the effect of erasing the contract retroactively as if it had never existed. In termination, particularly where the construction has been completed to an extent the landowner cannot refuse, the economic value of the work carried out by the contractor and its rights to the independent units agreed to be left to it are taken into account.
In this case, the level of rights the contractor has earned, which independent units or land shares the landowner is obliged to transfer and the compensation the parties may claim from each other are determined by expert examination.
However, the damage suffered by the landowner due to the contractor's delay may also be assessed separately.
Court of Cassation practice accepts that a land-for-flat construction agreement can be ended by agreement of the parties or by court decision (Court of Cassation, 23rd Civil Chamber, E. 2015/3119, K. 2018/2150, 13.03.2018).
If the contractor does not accept the landowner's intention to terminate, particularly where the land registry records also need to be changed, the dispute must be resolved through the courts.
11. Withdrawal from the Contract
In the case of withdrawal from the contract, the aim is to return the parties, as far as possible, to the position they were in before the contract was concluded. For example, if
- the landowner has transferred the land or a land share to the contractor,
- and the contractor has not completed the construction,
then if the contract is ended retroactively, the legal basis for the title transfers made to the contractor ceases to exist. In this case, the landowner may seek cancellation of title and registration.
However, this does not mean that in every dispute all title registrations will be cancelled directly. The level of construction, the work carried out by the contractor, the provisions of the contract and any transfers to third parties must be assessed separately.
12. Where the Construction Is Largely Complete
One of the most important points in land-for-flat construction disputes is the level the construction had reached on the date the contract is ended. While ending the contract by withdrawal is more readily accepted when the construction is at an initial or low level, the same result may not always be fair where the building is largely complete.
Indeed, according to the Grand General Assembly on the Unification of Case Law of the Court of Cassation, where the contractor is in default through its own fault, applying the retroactive consequences of ending the contract (withdrawal) is in principle possible; however, where the nature and particular features of the case justify it, it may be decided, having regard to the principle of good faith in Article 2 TCC, that termination should take effect for the future (Court of Cassation Grand General Assembly on the Unification of Case Law, E. 1983/3, K. 1984/1, 25.01.1984).
In practice, the completion rate of the construction emerges as an important criterion in this assessment.
In Court of Cassation practice, completion of the construction at a level of 90% or more is accepted as an important indicator for termination with effect for the future; however, it is not correct to resolve the dispute solely on the basis of a single mathematical ratio.
The court assesses together
- the completion level of the construction,
- the nature of incomplete and defective work,
- the provisions of the contract,
- the degree of fault of the parties,
- the actual situation on the date of termination,
- whether the building can be used economically and legally,
- the consequences of termination for the parties.
13. Conclusion
The contractor's failure to perform its obligation under a land-for-flat construction agreement does not leave the landowner without remedy. Depending on the circumstances of the case, there are several routes the landowner can take. However, which route is chosen is of great importance, particularly with regard to the completion level of the construction and the title transfers previously made to the contractor.
Therefore, where the contractor fails to complete the work under a land-for-flat construction agreement, the first step is to determine which choice best serves the landowner's interests.
This determination must be made in each case in light of the special provisions of the contract, the actual level of construction, the contractor's fault, the title transfers made and any assignments to third parties.